Weybourne, Church of All Saints
New Kitchenette and Toilet
Project Architect: Iain Walker
Project Team: Weybourne PCC (Client), Nicholas Warns Architect Ltd (Architect) Draper & Nichols Ltd (Contractor), Philip Waller Consulting Ltd (CDM Coordinator), Wildlife Consultant
Grade II* Listed Building
Completion Date: December 2017
Repairs carried out:
- The construction of an Accessible Toilet and storage in the Tower.
- A Kitchenette enclosed in a cupboard in the south west corner of the Nave.
- Install new mains water supply and foul drainage to serve the new facilities.
We provided a full service including concept and detailed design drawings; application for Faculty; provision of full tender documents, including schedule of work and analysis of tender returns to appoint Contractors; contract administration to include pre-start meetings and coordination of the wider project team; regular on-site meetings with minutes issued; issuing of Architects Instructions for variations; issuing Interim Payment Certificates/Practical Completion Certificate/ Release of Retention for Final Payment; site visits to monitor progress between meetings; handover to Client.